Replacement of power transformer T-1 at the 110/10 kV Palemonas transformer substation

AB "Energijos skirstymo operatorius"

UAB Ekobana, acting as a contractor, carried out the replacement of power transformer T-1 at the 110/10 kV Palemonas transformer substation, supplied the equipment, and prepared a detailed design.

THE SCOPE OF THE CONTRACT:

  • Preparing the detailed design
  • Disassembly of the old 110/10 kV 16 MVA power transformer, its transportation to the facilities of AB ESO and conservation
  • Delivering a new 110/10/10 kV 25 MVA power transformer, its assembly, and testing
  • Commissioning works

UAB Ekobana fulfilled the contract within budget and strictly in accordance with all the technical conditions laid down in the contract. 

2017
year started
8
month implementation deadline
2017
year of project delivery